Next week at this project, we are scheduled to install precast concrete abutments and precast concrete beams. This requires the closures of Route 5 (Oaklawn Avenue), from Brayton Avenue to Sherman Avenue, Sunday-Thursday nights from 9 p.m. to 5 a.m., and alternating lanes on Route 37, from Glen Hills Drive to I-295, Sunday-Thursday nights from 8 p.m. to 5 a.m. Demolition shielding installation will also involve the closures of Route 2 (New London Avenue), from Sockanosset Cross Road to Howard Avenue, Monday-Thursday nights from 10 p.m. to 5 a.m., and alternating lanes to install temporary lighting on Route 37, from Glen Hills Drive to Power Road, Monday-Thursday nights from 8 p.m. to 5 a.m. Motorists can also expect alternating lane closures in a moving operation for striping along Route 37, from I-295 to Glen Hills Drive, New London Avenue to Power Road, and from Jefferson Boulevard to Post Road, Tuesday or Wednesday, from 9 a.m. to 3 p.m.
On Friday night, January 16, we are scheduled to install a new traffic pattern at the Route 37 and New London Avenue (Route 2) intersection for the start of bridge demolition. This will require the closures of Route 2, from Sockanosset Cross Road to Howard Avenue, from 10 p.m. to 5 a.m., and alternating lanes along Route 37, from Glen Hills Drive to Power Road, from 8 p.m. to 5 a.m. In case of rain, the operation will take place on Saturday night, January 17. Please follow signed detours during all closures.
|